8/29/2022
Things will continue to be very busy and congested over the next couple of weeks, but there will be three flaggers onsite to keep things moving. Once a paving date has been selected, residents will be notified since access to homes and driveways will not be available during paving.
Dover Segment of Ontario Rd
Construction Items Completed: Sewer main installation has begun and is planned for completion on Tuesday.
Up Next: Several hundred feet of roadway will be rebuilt and prepared for final paving next week. Work to repair the failed section on Ontario Street west of Lower Syringa will occur currently, and both phases of the project are planned for completion next week.
Planned completion date: September 7, 2022
Sandpoint Segment of Ontario Rd
Construction Items Completed: Pavement removal and placing embankment for widening has been completed.
Up Next: Avista will be completing a gas service installation on Ontario near Northview Drive. Roadway grading will continue through this week. Paving will occur next week.
Planned completion date: September 7, 2022