Re: Ontario Street Update

 

Things will continue to be very busy over the next week, but there will be three flaggers onsite to keep things moving. Paving is scheduled to occur on Thursday, September 8 and Friday, September 9. On the days that paving occurs, Ontario Street must be closed for 2-4 hours during paving.  Residents will have access to their homes by foot during paving, rolling and pavement cooling. If you require any special accommodations, please notify the Dover City Clerk at (208)265-8339 so arrangements can be made.

 

Dover Segment of Ontario Rd

Construction Items Completed: Sewer main installation has been completed. Several hundred feet of roadway has been rebuilt and prepared for final paving next week.

Up Next: Work to repair the portion of Ontario Street west of the train tracks has been started. The contractor will dig out and rebuild the base section today (9/2), and Ontario St west of the tracks will remain open for the holiday weekend.  Fine grading and paving of the entire project are set to occur next week.

Planned completion date: September 9, 2022

 

Sandpoint Segment of Ontario Rd

Construction Items Completed: Pavement removal and placing embankment for widening has been completed.

Up Next: Fine grading and paving of the entire project are set to occur next week.

Planned completion date: September 9, 2022