August 19, 2022

August 19th, 2022 @ 9:11am

Dover residents,

Please see the update below from our City Engineer:

Dover Segment of Ontario Rd

Construction Items Completed: Asphalt removal is complete. Sewer main installation has begun.

Up Next: Sewer main extension and service installations between Canoe Cove and Dover/Sandpoint City limit will continue through early next week. After sewer installation, several hundred feet of roadway will be rebuilt and prepared for final paving the last week of August.

Planned completion date: August 30, 2022

 

Sandpoint Segment of Ontario Rd

Construction Items Completed: Culvert extension work and embankment placement for widening is in progress.

Up Next: Paving will begin near the end of August.

Planned completion date: Sept 2, 2022