12″ Water Main Extension Update

September 28, 2022

September 28th, 2022

Please see the following updates from the City Engineer:

The overall project schedule remains the same with an estimated completion date of October 12th, 2022.

Water Main Installation Updates: The 12” water main in the field area as well as the 12” valve and 90-degree elbow was successfully installed last Friday. There is a small portion left to install that is anticipated to be completed by this Friday. The crew plans to start the next section of pipe at the existing reservoir and work down the hill soon.

Compaction Testing: Has been tentatively scheduled for this week for testing on the trenching.

Clearing and grubbing: This was completed last week. The water main corridor is now prepped for trenching.

In case of an unplanned water outage: The city has obtained a water truck that for emergency use, should the situation arise. The water has been tested and is being monitored so that it remains safe to drink if needed.