October 7th, 2022
RE: 12” Water Line Extension Update:
Dear Dover residents,
Please see the following updates from the City Engineer:
The overall project schedule remains the same with an estimated completion date of October 12th, 2022.
Water Main Installation Updates: The tie-in for the existing reservoir is completed, and work will continue down the hill.60% of the field restoration has been completed, but the field trenching and backfill still needs topsoil.
Compaction Testing: The schedule is being coordinated.
Disinfection & pressure testing: The line will be disinfected before it is pressure tested. Pressure testing is planned for next week.
In case of an unplanned water outage: The city has obtained a water truck that for emergency use, should the situation arise. The water has been tested and is being monitored so that it remains safe to drink if needed.